Time and Work: Practice Questions for Competitive Exams

Time and Work: Key Concepts, Formulas, and Practice Questions

Time and Work is an important concept in quantitative aptitude and is frequently tested in competitive exams like SSC, Banking, and CAT. This topic is based on calculating how long it takes for a person or a group of people to complete a task, either alone or working together. The problem types generally involve rates of work, time, and efficiency.


Key Concepts & Formulas:

1. Work Formula

  • Work Done = Rate of Work×Time\text{Rate of Work} \times \text{Time}Rate of Work×Time
    • The rate of work can be expressed as how much of a task is completed in a unit of time.

2. Time and Work Relation

  • If a person can complete a task in xxx days, the rate of work is 1x\frac{1}{x}x1​ (i.e., they complete 1x\frac{1}{x}x1​ of the task per day).
  • If AAA can complete the work in xxx days, then BBB can complete the same work in yyy days, the combined work rate when both work together is: Rate of work (A and B together)=1x+1y\text{Rate of work (A and B together)} = \frac{1}{x} + \frac{1}{y}Rate of work (A and B together)=x1​+y1​ The time taken for them to complete the work together is: T=1(1x+1y)T = \frac{1}{\left(\frac{1}{x} + \frac{1}{y}\right)}T=(x1​+y1​)1​

3. Work Efficiency

  • Efficiency refers to the amount of work done by a person in a unit of time. If AAA completes the work in xxx days, and BBB completes the same work in yyy days, their individual efficiencies are:
    • Efficiency of A = 1x\frac{1}{x}x1​
    • Efficiency of B = 1y\frac{1}{y}y1​
  • Combined Efficiency = 1x+1y\frac{1}{x} + \frac{1}{y}x1​+y1​

Time and Work Problems Types:

  1. Individual Work Problems: Finding the time taken by a person to complete a task.
  2. Combined Work Problems: When two or more people or machines work together.
  3. Work Done in a Given Time: Finding the portion of work completed by individuals or teams in a specific time.
  4. Work Done by Multiple People in the Same Time: Finding the combined efficiency of multiple people working together.

25 Practice Questions on Time and Work

Basic Questions:

  1. A can complete a job in 12 days. B can complete the same job in 18 days. How long will they take to complete the job together?
  2. A and B can do a piece of work in 6 and 9 days respectively. How long will it take for them to complete the work together?
  3. If A works twice as fast as B, and together they complete a job in 12 days, how long would A take to finish the work alone?
  4. A can finish a work in 20 days. B can finish it in 30 days. How long will they take to finish the work together?
  5. A and B can complete a task in 20 and 30 days respectively. How long will it take for them to complete the task if they work alternately?

Intermediate Questions:

  1. A and B can complete a work in 12 days and 18 days respectively. If they work together for 6 days, how much of the work is left?
  2. A can complete a work in 10 days, and B can complete it in 15 days. After working together for 4 days, how much work is left?
  3. A can complete a work in 8 hours, B in 12 hours, and C in 15 hours. How long will it take for them to complete the work together?
  4. A and B together can complete a work in 6 days. If A works alone for 2 days, how many more days will B take to complete the remaining work?
  5. If A can complete a work in 12 days and B can complete it in 18 days, how many days will they take to finish half of the work together?

Advanced Questions:

  1. A, B, and C can complete a work in 10, 15, and 20 days, respectively. How long will it take for all three to finish the work together?
  2. If 3 people, A, B, and C, can complete a work in 4 days, 6 days, and 12 days, respectively, how long will it take for A to complete the work alone if they work together for 2 days?
  3. A can complete a work in 6 days, B in 8 days, and C in 12 days. If they work together for 2 days, how long will it take for C to finish the remaining work alone?
  4. If A and B can do a job in 8 days, B and C can do the same job in 12 days, and C and A can do it in 14 days, how many days will A, B, and C take to finish the job together?
  5. A can complete a job in 10 hours. B takes 12 hours, and C takes 15 hours. If they work together for 6 hours, how much work is completed?

Work and Wages Questions:

  1. A is paid ₹100 for 10 hours of work. How much will A be paid for 15 hours of work?
  2. If 5 men can complete a task in 8 days, how long will 3 men take to complete the same task?
  3. A works for 5 hours a day and B works for 6 hours a day. If A completes a task in 10 days and B completes it in 12 days, how long will it take for both A and B working together to complete the task?
  4. If 4 men can complete a work in 24 days, how many men are required to complete the same work in 12 days?
  5. A can do a piece of work in 15 days and B in 20 days. They work together for 5 days. How much work is left?

Special Questions:

  1. If A and B working together can finish a task in 15 days, and A alone takes 25 days, how long will B take to finish the work alone?
  2. A can finish a job in 5 days and B in 7 days. They work together for 3 days, then A leaves. How long will it take B to finish the remaining work?
  3. A can do a work in 8 days, B in 10 days, and C in 12 days. If all of them start the work together, how long will it take them to complete the work?
  4. If 3 workers A, B, and C can complete a task in 12, 15, and 18 days respectively, how long will it take if all three work together for 4 days and then A leaves?
  5. A, B, and C can do a work in 5, 10, and 15 days, respectively. How long will it take them to finish the work if A and B work together for 2 days, and then C joins them?
Answer

Answers to Time and Work Questions:

1. A can complete a job in 12 days. B can complete the same job in 18 days. How long will they take to complete the job together?

  • Answer: Time together=1112+118=1336+236=1536=7.2days\text{Time together} = \frac{1}{\frac{1}{12} + \frac{1}{18}} = \frac{1}{\frac{3}{36} + \frac{2}{36}} = \frac{1}{\frac{5}{36}} = 7.2 \, \text{days}Time together=121​+181​1​=363​+362​1​=365​1​=7.2days

2. A and B can do a piece of work in 6 and 9 days respectively. How long will it take for them to complete the work together?

  • Answer: Time together=116+19=1518=3.6days\text{Time together} = \frac{1}{\frac{1}{6} + \frac{1}{9}} = \frac{1}{\frac{5}{18}} = 3.6 \, \text{days}Time together=61​+91​1​=185​1​=3.6days

3. If A works twice as fast as B, and together they complete a job in 12 days, how long would A take to finish the work alone?

  • Answer:
    Let A=2BA = 2BA=2B.
    Together, they take 12 days: 1x+1x2=112\frac{1}{x} + \frac{1}{\frac{x}{2}} = \frac{1}{12}x1​+2x​1​=121​ Solving gives: x=24x = 24x=24
    So, A would take 24 days to finish the work alone.

4. A can finish a work in 20 days. B can finish it in 30 days. How long will they take to finish the work together?

  • Answer: Time together=1120+130=1560=12days\text{Time together} = \frac{1}{\frac{1}{20} + \frac{1}{30}} = \frac{1}{\frac{5}{60}} = 12 \, \text{days}Time together=201​+301​1​=605​1​=12days

5. A and B can complete a task in 20 and 30 days respectively. How long will it take for them to complete the task if they work alternately?

  • Answer:
    The time taken when working alternately is calculated by taking their individual rates and adding them.
    In one cycle (one day of A’s work + one day of B’s work), they complete: 120+130=560=112\frac{1}{20} + \frac{1}{30} = \frac{5}{60} = \frac{1}{12}201​+301​=605​=121​ Thus, in one cycle (2 days), they complete 112\frac{1}{12}121​ of the task.
    Total time = 12×2=24days12 \times 2 = 24 \, \text{days}12×2=24days.

6. A and B together can complete a work in 12 days and 18 days respectively. If they work together for 6 days, how much of the work is left?

  • Answer: Combined rate=112+118=536\text{Combined rate} = \frac{1}{12} + \frac{1}{18} = \frac{5}{36}Combined rate=121​+181​=365​ In 6 days, they complete: 536×6=3036=56\frac{5}{36} \times 6 = \frac{30}{36} = \frac{5}{6}365​×6=3630​=65​ Thus, the remaining work is 156=161 – \frac{5}{6} = \frac{1}{6}1−65​=61​.

7. A can complete a work in 10 days, and B can complete it in 15 days. After working together for 4 days, how much work is left?

  • Answer:
    Combined rate = 110+115=16\frac{1}{10} + \frac{1}{15} = \frac{1}{6}101​+151​=61​.
    Work done in 4 days = 16×4=23\frac{1}{6} \times 4 = \frac{2}{3}61​×4=32​.
    Work left = 123=131 – \frac{2}{3} = \frac{1}{3}1−32​=31​.

8. A can complete a work in 8 hours, B in 12 hours, and C in 15 hours. How long will it take for them to complete the work together?

  • Answer:
    Combined rate = 18+112+115=15120+10120+8120=33120=1140\frac{1}{8} + \frac{1}{12} + \frac{1}{15} = \frac{15}{120} + \frac{10}{120} + \frac{8}{120} = \frac{33}{120} = \frac{11}{40}81​+121​+151​=12015​+12010​+1208​=12033​=4011​.
    Time taken = 11140=40113.64hours\frac{1}{\frac{11}{40}} = \frac{40}{11} \approx 3.64 \, \text{hours}4011​1​=1140​≈3.64hours.

9. A and B together can complete a work in 6 days. If A works alone for 2 days, how many more days will B take to complete the remaining work?

  • Answer:
    Work done by A in 2 days = 26=13\frac{2}{6} = \frac{1}{3}62​=31​.
    Remaining work = 113=231 – \frac{1}{3} = \frac{2}{3}1−31​=32​.
    Time taken by B to complete the remaining work = 2316=4days\frac{\frac{2}{3}}{\frac{1}{6}} = 4 \, \text{days}61​32​​=4days.

10. If A can complete a work in 12 days and B can complete it in 18 days, how many days will they take to finish half of the work together?

  • Answer:
    Combined rate = 112+118=536\frac{1}{12} + \frac{1}{18} = \frac{5}{36}121​+181​=365​.
    Time to complete half the work = 12536=3610=3.6days\frac{\frac{1}{2}}{\frac{5}{36}} = \frac{36}{10} = 3.6 \, \text{days}365​21​​=1036​=3.6days.

11. A, B, and C can complete a work in 10, 15, and 20 days, respectively. How long will it take for all three to finish the work together?

  • Answer:
    Combined rate = 110+115+120=660+460+360=1360\frac{1}{10} + \frac{1}{15} + \frac{1}{20} = \frac{6}{60} + \frac{4}{60} + \frac{3}{60} = \frac{13}{60}101​+151​+201​=606​+604​+603​=6013​.
    Time taken = 11360=60134.62days\frac{1}{\frac{13}{60}} = \frac{60}{13} \approx 4.62 \, \text{days}6013​1​=1360​≈4.62days.

12. If 3 people, A, B, and C, can complete a work in 4 days, 6 days, and 12 days, respectively, how long will it take for A to complete the work alone if they work together for 2 days?

  • Answer:
    Combined rate for 2 days = 14+16+112=712\frac{1}{4} + \frac{1}{6} + \frac{1}{12} = \frac{7}{12}41​+61​+121​=127​.
    Work done in 2 days = 712\frac{7}{12}127​.
    Remaining work = 1712=5121 – \frac{7}{12} = \frac{5}{12}1−127​=125​.
    A’s rate is 14\frac{1}{4}41​.
    Time taken by A to complete the remaining work = 51214=53=1.67days\frac{\frac{5}{12}}{\frac{1}{4}} = \frac{5}{3} = 1.67 \, \text{days}41​125​​=35​=1.67days.

13. A can complete a work in 6 days, B in 8 days, and C in 12 days. If they work together for 2 days, how long will it take for C to finish the remaining work alone?

  • Answer:
    Combined rate = 16+18+112=724\frac{1}{6} + \frac{1}{8} + \frac{1}{12} = \frac{7}{24}61​+81​+121​=247​.
    Work done in 2 days = 724×2=712\frac{7}{24} \times 2 = \frac{7}{12}247​×2=127​.
    Remaining work = 1712=5121 – \frac{7}{12} = \frac{5}{12}1−127​=125​.
    C’s rate is 112\frac{1}{12}121​.
    Time taken by C to finish the remaining work = 512112=5days\frac{\frac{5}{12}}{\frac{1}{12}} = 5 \, \text{days}121​125​​=5days.

14. If A and B can do a job in 8 days, B and C can do the same job in 12 days, and C and A can do it in 14 days, how many days will A, B, and C take to finish the job together?

  • Answer:
    Use the system of equations method. A+B=18,B+C=112,C+A=114A + B = \frac{1}{8}, \quad B + C = \frac{1}{12}, \quad C + A = \frac{1}{14}A+B=81​,B+C=121​,C+A=141​ Adding these three equations: 2A+2B+2C=18+112+1142A + 2B + 2C = \frac{1}{8} + \frac{1}{12} + \frac{1}{14}2A+2B+2C=81​+121​+141​ Solving the equation gives: A+B+C=14(Time taken for all to finish the work together)=4daysA + B + C = \frac{1}{4} \quad \text{(Time taken for all to finish the work together)} = 4 \, \text{days}A+B+C=41​(Time taken for all to finish the work together)=4days

15. A can do a piece of work in 10 hours. B takes 12 hours, and C takes 15 hours. If they work together for 6 hours, how much work is completed?

  • Answer:
    Combined rate = 110+112+115=14\frac{1}{10} + \frac{1}{12} + \frac{1}{15} = \frac{1}{4}101​+121​+151​=41​.
    Work done in 6 hours = 14×6=32\frac{1}{4} \times 6 = \frac{3}{2}41​×6=23​.

16. A is paid ₹100 for 10 hours of work. How much will A be paid for 15 hours of work?

  • Answer:
    Rate of payment = 10010=10\frac{100}{10} = ₹1010100​=₹10 per hour.
    For 15 hours, A will be paid 10×15=15010 \times 15 = ₹15010×15=₹150.

17. If 5 men can complete a task in 8 days, how long will 3 men take to complete the same task?

  • Answer:
    Total work done by 5 men in 8 days = 5×8=405 \times 8 = 405×8=40 men-days.
    Time taken by 3 men to complete the work = 403=13.33days\frac{40}{3} = 13.33 \, \text{days}340​=13.33days.

18. A works for 5 hours a day and B works for 6 hours a day. If A completes a task in 10 days and B completes it in 12 days, how long will it take for both A and B working together to complete the task?

  • Answer:
    A’s rate = 110\frac{1}{10}101​ of the task per day.
    B’s rate = 112\frac{1}{12}121​ of the task per day.
    Combined rate = 110+112=1160\frac{1}{10} + \frac{1}{12} = \frac{11}{60}101​+121​=6011​.
    Time taken together = 11160=60115.45days\frac{1}{\frac{11}{60}} = \frac{60}{11} \approx 5.45 \, \text{days}6011​1​=1160​≈5.45days.

19. If 4 men can complete a work in 24 days, how many men are required to complete the same work in 12 days?

  • Answer:
    Work done by 4 men in 24 days = 4×24=964 \times 24 = 964×24=96 men-days.
    Time required by xxx men to complete the same work in 12 days = x×12=96x \times 12 = 96x×12=96.
    Solving gives x=8x = 8x=8.

20. A can do a piece of work in 15 days and B in 20 days. They work together for 5 days. How much work is left?

Answer:
Combined rate = 115+120=760\frac{1}{15} + \frac{1}{20} = \frac{7}{60}151​+201​=607​.
Work done in 5 days = 760×5=3560=712\frac{7}{60} \times 5 = \frac{35}{60} = \frac{7}{12}607​×5=6035​=127​.
Work left = 1712=5121 – \frac{7}{12} = \frac{5}{12}1−127​=125​.